STN: The Uttar Pradesh Metro Rail Corporation Limited (UPMRCL) has issued a civil tender for the construction of a depot-cum-workshop at Mall Road. This facility will serve Agra Metro Corridor 2, which connects Agra Cantt to Kalindi Vihar.
The estimated cost of the contract is ₹177.58 crore. The selected contractor must complete the work within 18 months.
The depot will support train operations on Agra Metro Corridor 2. It will handle train stabling, inspection, and maintenance work.
Tender Details for Agra Metro Corridor 2
UPMRCL released the tender on 13 February 2026. The last date to submit bids is 16 March 2026.
Here are the key details:
- Tender Issue Date: 13 February 2026
- Closing Date: 16 March 2026
- EMD: ₹3.55 crore
- Tender ID: 2026_UPMRC_266535_
- Tender No.: AGCC-08
- Estimated Cost: ₹177.58 crore
- Contract Duration: 18 months
UPMRCL will evaluate the bids as per its procurement guidelines.
Scope of Work Under Agra Metro Corridor 2 Depot Project
The contract covers civil, structural, and system works. The contractor will build a full depot-cum-workshop facility at Mall Road.
The scope includes:
Civil and Structural Works
- Construction of buildings and structural components
- Pre-engineered building (PEB) structures
- Architectural finishing works
- Boundary wall construction
- Internal road development
- External development works
Utility and System Installations
- Plumbing and drainage systems
- Electrical and mechanical installations
- Ventilation and Air Conditioning (VAC) systems
- Fire detection and firefighting systems
The depot will support train operations. It will provide space for train parking. It will also allow routine inspection and repair work.
This facility is important for safe and regular metro services.
Overview of Agra Metro Project
The Agra Metro project covers around 30 km under Phase 1. It includes two corridors:
- Line 1: Sikandra to Taj East Gate (14.25 km, 14 stations)
- Line 2: Agra Cantt to Kalindi Vihar (15.40 km, 15 stations)
Line 2 is also known as Agra Metro Corridor 2. The Mall Road depot will serve this line.
At present, a 5.2 km priority section of Line 1 is operational. It runs between Taj East Gate and Mankameshwar. This section connects major tourist areas, including the Taj Mahal.
The development of the depot will help speed up progress on Corridor 2. It will ensure trains operate smoothly once the corridor becomes operational.
Why the Mall Road Depot Matters
A metro system cannot run without a depot. The depot acts as the control and maintenance center. It supports daily operations.
The Mall Road depot will:
- Provide space for train stabling
- Support inspection and testing
- Enable scheduled maintenance
- Improve service reliability
Once completed, Agra Metro Corridor 2 will improve daily travel. It will reduce traffic on major roads. It will also improve connectivity between Agra Cantt and Kalindi Vihar.
The project will help residents and visitors move across the city more easily.
FAQ – Agra Metro Corridor 2 Depot Project
A: A metro depot stores trains when they are not in service. It also handles maintenance, cleaning, and inspection work.
A: The depot will be built at Mall Road in Agra. It will support operations of Corridor 2.
A: UPMRCL has set the completion timeline at 18 months from the date of contract award.
A: Eligible contractors with experience in civil, structural, and system works can submit bids as per tender conditions.
A: Agra Metro Corridor 2 is 15.40 km long and includes 15 stations.
A: It will improve public transport. It will reduce road congestion. It will offer faster travel between Agra Cantt and Kalindi Vihar.